PROJECTS THAT NEED FINANCING

RECONSTRUCTION OF KYIV OBLAST

At the beginning of the full-scale invasion, Kyiv Oblast faced active hostilities and mass shelling. Hundreds of thousands of the oblast’s residents were forced to leave their homes, and those who remained faced power, water, and heating issues. After the de-occupation, Ukrainian energy workers were able to restore power to the people in a month and a half, but in October, Russia began deliberately targeting energy infrastructure, and hundreds of thousands of people again found themselves on the brink of a humanitarian disaster.

Ukrainian energy workers can restore power, but, unfortunately, endless destruction has exhausted their supplies of equipment, so they need help. Energy workers have a ready-made plan to restore the power grid of Kyiv Oblast, but they need equipment to do it. Here you can see the list of necessary equipment and make your contribution to saving the lives of Kyiv Oblast residents.
Unit Name Unit Quantity Costs, USD
Power transformer 110 kV 63000 kVA 2 3 010 540
Power transformer 35 kV 10000 kVA 4 1 091 250
Power transformer 35 kV 16000 kVA 2 829 350
Power transformer 35 kV 6300 kVA 1 245 530
Power transformer 35/10 kV 10000 kVA 2 545 620
Circuit breaker SF6 10 190 970
Vacuum circuit breaker 10 kV for bay КМ-1Ф 3 9 820
Vacuum circuit breaker 35 kV ВР35НСМ-35-20-1600У1 2 24 550
Disconnector 110 kV 8 20 730
Voltage transformer 110 kV 7 48 210
Current transformer 110 kV 21 123 990
Current transformer 10 kV 10 1 360
Surge arrester 110 kV 10 5 890
Surge arrester 110 kV 15 640
Concrete complete transformer secondary substations 2*630 kVA 10 1 527 750
Complete switchgear 3 1 728 460
Other (reactors, capacitors, oil, foundations, portals) 64,43 289 210
Telemechanics and protection (systems, panels, modules, blocks, relays) 2 975 2 978 740
Control cable 2 317 46 470
Pole insulator 147 19 840
Bolts, nuts, washers, etc 280,5 1 530
Clamps 518 4 030
Poles 35-110 kV 642,15 4 283 070
Wires aluminum steel, Aero-Z 70-400 mm 530,41 4 850 600
Accessories, insulators for non-insulated wire 1 126 9 430
Power cable 78,87 2 358 140
Cable joints 2 078 302 500
Auto tower TA-60 4*4 with ALTEC installation 2 654 750
A set of tools, devices and protective equipment for work under voltage 10 230 803 390
Total: $26 006 360
GRID RECONSTRUCTION OF IRPIN REGION
Help is urgently needed!
During the Russian occupation, the city of Irpin was subjected to mass shelling and experienced heavy fighting. As a result, hundreds of homes were damaged and destroyed in the city, and stable powerstill cannot be restored as, since October, Russia has been deliberating striking power facilities making repairs effectively impossible for Ukrainian energy workers.
CORPORATE APPLICATION
Sign up on our website to help restore the damaged power infrastructure of Ukraine so that we can contact you and start our cooperation right now
Request page